1. Rate Agreement
1.1 Agreement on rates — All rates must be agreed upon and documented with either the Contracts Manager or Supervisor before work commences on any job. The rates will remain fixed unless otherwise renegotiated in writing.
1.2 Inclusive scope of rates — The agreed rates cover all costs associated with travel within a 30-mile radius of Bournemouth, including labour time, transport costs, and standard tools and equipment required for the job.
2. Mileage and Travel Expenses
2.1 Mileage outside 30 miles — Travel beyond a 30-mile radius from Bournemouth may be eligible for reimbursement at £0.45 per mile (each way), measured on the most direct route from Bournemouth to the worksite and back. This does not apply to subcontractors on price work or pre-agreed fixed rates, where travel costs are included within the agreed pricing.
2.2 Approval of additional travel — Any significant travel exceeding the 30-mile radius should be pre-approved in writing by the Contracts Manager or Supervisor to ensure eligibility for reimbursement.
3. Work Orders (WO)
3.1 Work order issuance — A Work Order will be issued by the Company before the start of any job, including site location, job description and scope, job reference number, WO number for invoicing, and the agreed total price for the job.
3.2 Work order amendments — Any changes to the job scope or price must be documented and authorised by the Contracts Manager or Supervisor, with an updated WO issued.
4. Invoice Layout and Payment Terms
4.1 Invoice presentation — Invoices must be presented on a per-job basis and include the total amount (all labour, materials, and any travel beyond the 30-mile radius) plus reference to the relevant WO number (e.g. WO1234) and the worksite address.
4.2 Format of invoice — Invoices should be submitted digitally (PDF preferred) with an itemised breakdown for easy verification. Failure to provide an itemised invoice may delay payment.
4.3.1 Standard payment terms — The Company will aim to process payments within 30 days of receiving a valid invoice, provided all required documentation, such as job sheets, has been correctly submitted.
4.3.2 Weekly payment terms for lower-value invoices — Weekly payments may be offered if pre-approved by management. These invoices must be submitted to repairs@grwestbuild.co.uk by Monday to be processed for payment the following Wednesday (7 working days). Weekly payment is an exception and must be pre-agreed in writing; otherwise the general 30-day payment terms apply.
5. Materials and Plant Hire
5.1 Pre-approval for additional costs — All materials and plant hire costs must be pre-approved by the Project Manager or Supervisor and itemised separately on the WO before invoicing.
5.2 Invoice requirements for materials — Approved materials or plant hire should be itemised and priced separately from labour on the invoice, including receipts where applicable.
6. Training Requirements
6.1 Site-specific training — Certain sites may require specific courses or certifications for access. The Subcontractor is responsible for ensuring they meet these training requirements. G.R. Westbuild Ltd is not obligated to cover these costs but may do so at its discretion. All glazing works carried out for G.R. Westbuild Ltd must be undertaken by contractors who hold a valid MTC or NVQ qualification for the entire duration of this agreement.
6.2 Training cost policy — Any training costs covered by the Company must be pre-approved in writing, and the Subcontractor agrees to meet and comply with all site training requirements.
7. Health and Safety Compliance
7.1 Standards and compliance — G.R. Westbuild Ltd upholds strict health and safety standards. The Subcontractor is expected to follow all health and safety procedures as outlined by the Company and UK legislation, including the Health and Safety at Work Act 1974.
7.2 Personal protective equipment — The Company will supply all necessary PPE free of charge. The Subcontractor is responsible for maintaining and returning the PPE when no longer working with the Company.
7.3 Breach of health and safety — Any serious or repeated breach of health and safety regulations may result in immediate termination of this agreement, in addition to potential legal consequences under UK law.
8. Warranties and Indemnities
8.1 Quality assurance and warranty — The Subcontractor guarantees a 12-month warranty on workmanship for all completed tasks. The Company expects a high standard of quality for all work performed.
8.2 Material quality warranty — If the Subcontractor provides materials, they are responsible for ensuring these materials meet a minimum standard of quality, with a 12-month warranty on materials used.
9. Data Protection and GDPR Compliance
9.1 Company compliance with GDPR — G.R. Westbuild Ltd is committed to protecting the privacy and security of personal data and adheres to the General Data Protection Regulation (GDPR) and the Data Protection Act 2018, with strict policies to ensure data is handled lawfully, fairly and transparently.
9.2 Subcontractor obligations — Subcontractors are required to follow GDPR principles and comply with all relevant data protection regulations when handling personal data provided by G.R. Westbuild Ltd, its clients, or other parties connected with contracted projects, taking appropriate technical and organisational measures to protect data and maintaining confidentiality.
9.3 Breach of data protection — Failure to comply with GDPR or breach of data protection policies may lead to termination of this agreement and potential legal consequences. Data breaches must be reported immediately to the Company in line with GDPR's mandatory reporting requirements.
10. Termination of Agreement
10.1 Termination with notice — Either party may terminate this agreement with a written notice period of 5 days. This agreement may be terminated without notice in cases of gross misconduct or significant breaches of contract terms.
10.2 Immediate termination — The Company reserves the right to terminate this agreement immediately in cases of health and safety violations, unauthorised costs, or failure to comply with Company policies.
11. Procedures and Policies
11.1 Familiarisation with policies — The Subcontractor must familiarise themselves with G.R. Westbuild procedures and policies, including documentation requirements, site rules, and any client-specific protocols.
11.2 Responsibility for documentation — The Subcontractor is responsible for ensuring all job sheets, paperwork and other required documents are accurately completed and returned promptly. Failure to follow these processes may lead to delays in payment.
12. Duration and Review
12.1 Annual review and amendments — This agreement is subject to annual review by G.R. Westbuild Ltd, during which terms may be evaluated for renewal or modification. The Company also reserves the right to amend this agreement at any time, with amendments communicated in writing with reasonable notice. In the event of any significant change, the Subcontractor will be given the opportunity to discuss and confirm acceptance of the revised terms. Continued work following such notification constitutes acceptance of the amended agreement.
13. Site Conduct and Representation
13.1 Professional behaviour — When working on-site, subcontractors and their employees are expected to represent G.R. Westbuild Ltd with the highest standards of professionalism: maintaining respectful and courteous behaviour at all times, avoiding inappropriate language, refraining from loud music or other disruptive activities, following designated non-smoking policies, and dressing appropriately for the construction environment.
13.2 Compliance with site rules — All subcontractors must adhere strictly to site rules, including those set by G.R. Westbuild Ltd's clients. Violations may result in removal from site and could impact future working arrangements with the Company.
13.3 Whistleblowing — If a subcontractor or employee observes unsafe practices, unethical behaviour, or conduct that could harm the Company's reputation, they are encouraged to report this confidentially to management. All reports will be taken seriously and investigated in line with Company policies, with no retaliation against individuals who report concerns in good faith.
13.4 Employee identification for site access — G.R. Westbuild Ltd may request a list of all employees assigned to a project, along with digital photos of each individual, to produce photographic identification required for site access on specific projects. Subcontractors agree to supply accurate, up-to-date information upon request.